Drive a 10d nail.
Roof tile installation method.
Use two tiles to determine the spacing required for the battens.
This method has been disappearing from the roofing industry.
S certification training programs are designed to educate roofers and roofing professionals on code approved installation methods.
A minimum of a 3 inch overlap is required for the tiles.
Recently the national tile roofing manufacturers association ntrma changed its name to tile roofing institute.
Rake edge trim can be installed as the tile is laid along the gable edge or after the tile is in place.
Tiles can be nailed either directly into the roof sheathing or tiles with lugs can be nailed to battens.
The rake edge trim should be placed so the edge of the rake trim butts against the nose of the next course of field tile.
In january 1987 the roof tile committee of the frsa ntrma was commissioned to develop and write consensus guidelines for the installation of concrete and clay roof tiles.
Mortar down application uses a mixture of building and sharp sand with cement mix.
Follow these simple steps to install your clay tiles.
Double nail down application uses two ring shank nails.
Nails are the least expensive and most common method for attaching concrete and clay tiles.
Position the first tile on the batten with the crown facing up and center the tile from side to side.
Hip and ridge tiles are fastened to a metal channel which is nailed to the roof with stainless steel roofing nails.
Mortar is then installed to fill the gap between the tiles and the hip and ridge tiles.
This method has been largely.
Corrosion resistant nails must be minimum 11 gauge with 5 16 inch heads and long enough to penetrate the sheathing by 3 4 inch typically 8d nails.
Tri alliance concrete and clay roof tile installation manual 2015.
Add some mortar underneath the first clay tile to provide additional support.
Here are five of the most common methods to consider.
Re shingling an existing roof is the easiest method of installation for a diy homeowner.
The rake trim is universal and will fit either right or left rakes.
Sign up for email updates.
Tri offers classroom certification training and free hands on demonstrations.
If installing a new roof on a bare roof deck cut 6 inches off the first starter course shingle and apply the rest of it on the lower corner of the roof overlapping the rakes and eaves by 1 2 inch.